A public-private partnership meant to fix Bislig City's chronic water shortages hit a setback earlier this year. The Public-Private Partnership (PPP) Center issued a Notice of Failure of Bidding for the Bislig City Bulk Water Supply Project on April 28, 2026, a day after the bid submission deadline for the project's bulk water component closed with no winning offer.
What the project was meant to do
The Bislig City Bulk Water Supply Project, developed jointly by the Bislig City Water District (BCWD) and the national PPP Center, called for a private partner to design, finance, build, and operate a new bulk water facility with a minimum capacity of 10 million liters per day, sourced from the Burboanan River. The scope also included rehabilitating and expanding BCWD's existing distribution network. Under the proposed joint venture agreement, the winning partner would have operated the system alongside BCWD for 33 years, including the construction period. The PPP Center's own project documentation pegs the cost at roughly P710 million (about US$12.26 million).
The project has a long history. A Swiss challenge process for an earlier version of the plan was published in a national daily as far back as February 2013, but no qualified bidder came forward to contest the original proposal at that time. The version that failed bidding this April was a more recent attempt to revive the plan through the formal PPP Center process, with the Invitation to Qualify and Bid published and a submission deadline set for April 27, 2026 at noon.
Why Bislig needs it
BCWD's current system does not cover the whole city. The water district serves only 11 of Bislig's 24 barangays, according to the project's own planning documents, leaving much of the city dependent on other sources. Even within its service area, BCWD has had to ration supply and run water on an every-other-day schedule during dry spells, particularly in El Niño years, while the rainy season brings the opposite problem of high turbidity that degrades water quality at the source. A new bulk water facility drawing from the Burboanan River, paired with an upgraded distribution network, was designed to address both the coverage gap and the seasonal reliability problems in one project.
A companion project moved forward instead
The bulk water component was bid alongside a related but separate piece, the Bislig City Septage Project, which covers a wastewater treatment facility with a minimum capacity of 40 cubic meters per day plus desludging trucks. That component had a later submission deadline of April 29, 2026. Unlike the bulk water side, the septage project has continued to progress: Bislig Today previously reported that the PPP Center issued General Bid Bulletin No. 04-2026 for the septage project in July, indicating that piece of the plan is still moving through the standard bidding process even as the water component stalled.
What happens after a failed bidding round
A Notice of Failure of Bidding does not necessarily mean the bulk water project is dead. Under standard Philippine PPP and procurement procedures, a failed bidding round is typically followed either by a re-bidding process with revised terms or, in some cases, a negotiated procurement with a qualified party if repeated biddings fail to attract a compliant offer. As of this writing, neither BCWD nor the PPP Center has published a public update on which path the bulk water component will take next.
Bislig Today will report further developments on the bulk water project, including any rebidding announcement or revised timeline, as soon as BCWD or the PPP Center makes one public. Residents with questions about the project can reach BCWD's PBAC Secretariat at bisligcitywaterdistrict@gmail.com or (086) 853-2032.